East North Street weekly update May 4, 2012
Storm sewer installation along East North Street will be completed by the end of next week. The new 16” watermain has been tied in down by the Golden Fortune Restaurant. Gravel surfacing is being installed on Spruce Street. Spruce Street will then be temporarily opened and Cherry Avenue closed for storm sewer installation and watermain tie in.
Concrete paving, inlet construction, and grading along East North Street continues.
East Denver Street is now open from Cherry Avenue to Pine Street.
The public is welcome to our weekly construction meetings every Friday at 10am in the Wendy’s Restaurant on East North Street. There is also an Information Hotline that has been set up for the public to call and listen to weekly updates about construction and traffic control activities for the upcoming week. They also may leave a message with any questions and concerns they may have. They may also go to www.heavyconstructors.com for weekly updates and detailed traffic control maps.
Points of Contact for the Public:
(605)858-1451
Steve@heavyconstructors.com
Announcements
Heavy News now on the web!!
Heavy News will now be posted under "The Company" heading of our web page. All of our newsletters will be posted including some vintage newsletters from the mid 1990's! Go have a look!!<...
Read More>>Jackson Blvd. now on Facebook
Click to get the latest news and updates about Jacks...
Read More>>Current Projects
Testimonials
Millstone Family Restaruants
To Whom It May Concern:
Gustafson Builders have been working for my company for approximately 20 years. During this time, they have built 3 new buildings and completely renovated anot...
Read All Testimonials>>