East North Street weekly update April 27, 2012

 Water main installation along East North Street was delayed due to weather and should be finished by the end of next week. Traffic needing to use Spruce Street  will be diverted to Pine Street and Cherry Avenue respectively.

Storm sewer installation up Spruce Street has nearly been completed..  Concrete paving, inlet construction, and grading along East North Street continues.

East Denver Street is now open from Cherry Avenue to Pine Street.

The public is welcome to our weekly construction meetings every Friday at 10am in the Wendy’s Restaurant on East North Street. There is also an Information Hotline that has been set up for the public to call and listen to weekly updates about construction and traffic control activities for the upcoming week. They also may leave a message with any questions and concerns they may have. They may also go to www.heavyconstructors.com for weekly updates and detailed traffic control maps.

Points of Contact for the Public:

(605)858-1451
Steve@heavyconstructors.com

Announcements

Heavy News now on the web!!

 Heavy News will now be posted under "The Company" heading of our web page. All of our newsletters will be posted including some vintage newsletters from the mid 1990's! Go have a look!!<...

Read More>>

Jackson Blvd. now on Facebook

 Click to get the latest news and updates about Jacks...

Read More>>

Current Projects

Testimonials

TSP Three, Inc.

 To Whom It May Concern:

Over teh period of the last three years, TSP Three, Inc. has had the opprotunity to work with Gustafson Builders of Rapid City on a number of projects. The fir...

Read All Testimonials>>